BAKERSFIELD, Calif. — Paving is scheduled to begin on the nortside of 24th street between E and M streets on April 1. Paving will occur in the late afternoon and nightime.
Westbound lanes will be left open until 7 p.m.
The rest of the schedule is as follows:
- April 2: North side of the G, H and L street intersections. G Street will be closed on the north side of 24th Street at 4 p.m. H Street and L Street will be closed on the north side of 24th Street at 7 p.m.
- April 5: North side of the K Street, Chester Avenue, and M Street intersections. Chester Avenue will be closed on the north side of 24th Street at 7 p.m. and M Street will be closed on the north side of 24th Street at 8 p.m. K Street is currently closed.
- April 6-7: The two currently closed lanes on the north side of 24th Street between the intersections listed above. The adjacent westbound travel lane will be closed at 7 p.m. One lane will remain open to traffic.
Construction work may be postponed and rescheduled without notice due to weather or other unforeseen circumstances.